I feel like I blinked on the new dorm and classroom blocks for Empower International Academy and we've already started going vertical!
Rough grading done.
The foundations have been set and slabs poured.
The septic tank almost finished.
The soak pits dug.
The walls are going up.
Next up we've got back filling of the soak pits, superstructure walls going up, and fabrication of the door/window frames and timber trusses.