We had the ground breaking for the construction of Empower International Academy - Phase 2 in early February. We are extremely grateful for the student's who prayed over the construction team and joined us in the ground breaking as we kick off the construction of the new dormitories and classroom block.
During the design phase of this project we had no As-Built documents to go off for the existing infrastructure so we knew this project would potentially have a lot of subsurface investigation once the field work started.
Since breaking ground the crew has already found a wastewater pipe disconnected from the absorption pit, a water main line 2m off the anticipated location, and a soak pit about 7m from it's designed location.
We will have OAC field meetings every two weeks until project completion in January of 2024 and I'm very grateful for a cautious and patient field team we get to work with on this project!